This webpage is not updated over the weekend/overnight. For up-to-date information on traffic impacts, visit 511mn.org.
Traffic impacts
All traffic impacts are tentative and weather dependent. Access to South Frontage Rd. from Yosemite Ave. is permanently closed.
Current
Road closures
7 a.m. Wed, April 17 through Sat, May 18
- South Frontage Rd. is closed in both directions between Louisiana Ave. and Dakota Ave. to complete pavement and sidewalk work.
Upcoming
Information about upcoming traffic impacts will be posted as details become available.
About this project
MnDOT is reconstructing the Hwy 13 and Dakota Ave. intersection in Savage. The Dakota Ave. interchange construction project area includes Hwy 13 between the Hwy 13/Hwy 101 interchange and Quentin Ave.
Summary of work
- Construct new Hwy 13 bridge over Dakota Ave. to allow for safer and improved traffic flow
- Build new access ramps to/from Hwy 13 and Dakota Ave. to improve turning movements and reduce traffic backups
- Realign South Frontage Rd. for better access to/from Hwy 13
- Add a new north side frontage road to connect Dakota Ave. and Yosemite Ave.
The following tentative traffic impacts are anticipated and subject to change:
Spring-fall 2022
- 2 lanes open on Highway 13
- Temporary pavement
- Dakota Ave. bridge construction
- Road work on Hwy 13
Fall 2022-spring 2023
- 4 lanes open on Hwy 13
- Winter suspension
Spring-summer 2023
- 2 lanes open Hwy 13
- Dakota Ave. ramp construction
- Road work on Hwy 13
Summer 2023-winter 2023/2024
- 4 lanes on Hwy 13
- North and south frontage road construction
Spring 2024
- South frontage road paving, sidewalk work and landscaping