About this project
This project is complete, except for seal coats and permanent striping.
Summary of MnDOT work
- MnDOT resurfaced (mill, full-depth reclamation and overlay) Hwy 15 from the intersection of Hwy 12 in Dassel to the Meeker/Stearns County line near Kimball.
- Guardrail near the Kingston bridge was replaced to bring it into compliance.
- Thirty (30) culverts were lined along the project area and three culverts were replaced.
- This project required a detour (see map).
- A chip seal and permanent striping will be applied to the new pavement in the early summer of 2024.
Project update
May 10, 2024
- Chip and fog seal applications will take place on Hwy 15 beginning May 15
- Seat coats applications will take about 3 days and then temporary striping is applied to the roadway
- Work will then pause for two or more weeks until permanent striping operations can begin
- Drivers may encounter lane closures with flaggers directing traffic through the work zones; expect brief delays and allow extra travel time