About this project
Summary of work
- Resurface (asphalt) Hwy 23 from Pipestone to Russell.
- Culvert replacement near Florence.
- Bridge deck replacement in Pipestone.
- Culvert lining along the corridor.
Traffic impacts
- Planned detours during the bridge and culvert work.
- Florence culvert detour: Hwy 14 to Hwy 91
- Pipestone bridge detour: Hwy 75 to CR 8 to Hwy 23
Project update
- Thank you for attending the open house on May 10. Work is scheduled to get underway June 3.