Minnesota Department of Transportation

511 Travel Info

Hwy 67 Reconstruction

Clarkfield

About this project

Hwy 67 project map with detour

Summary of MnDOT work

  • MnDOT will be reconstructing Hwy 67, from just east of the intersection of Hwy 59 to 6th Street in Clarkfield. Replacement of storm sewer is included in the project.
  • The project includes replacement of sidewalks and the addition of pedestrian ramps to meet Americans with Disabilities (ADA) standards.
  • Alongside the MnDOT project, BNSF Railway will be replacing track at the intersection of Highway 59 and Highway 67.

Hwy 67 project map with detourDetours

  • Two detours are required for the MnDOT project. The detour of Hwy 59 will begin May 6 and last 2-3 weeks.
  • The detour of Hwy 67 will begin after Hwy 59 detour concludes. It will remain in place for the duration of the MnDOT project.
  • The added BNSF Railway project will require a separate detour of the Hwy 67 and Hwy 59 intersection. When MnDOT receives their project schedule, we will communicate the timeline and detour to the traveling public.

Project updates

May 10, 2024

  • The first detour (Hwy 59) began May 6.
  • Crews have been completing drainage work along Hwy 59 this week.
  • Work is tentatively scheduled to switch to Hwy 67 late next week.