About this project
Summary of work
- Resurface Hwy 68 from N Grant St. in Minneota to the intersection of Hwy 59 in Marshall. The city of Ghent is excluded from the project and will be resurfaced at a later date.
Traffic impacts
- Project will be done under traffic and a detour is not required.
- A flagging operation and pilot car will be in place; use caution and allow extra travel time.
Project update
May 10, 2024
- The start date has been rescheduled for May 20 (from May 13) due to weather and other unforeseeable circumstances.